Third phase of reconstruction of Miloje Pavlović street has started

Podgorica Development and Reconstruction Agency started reconstruction of the remaining part of around 1.100 m long street leading to Nikšić road on 18 May this year. The total value of works amounts to 907,214.45 euro, while the deadline for its completion is 180 days. The contractor is Gradnja-promet company from the town of Danilovgrad.

“Miloje Pavlović street will have two lanes, each one of them 3 m wide, and there will be 1.5 m wide pavements on both sides,“ the capital city told.

Around 350 m of the street was reconstructed in 2008, from the crossroads in Cetinje road to the intersection with Vojvođanska street. The value of those works amounted to 270.000 euro.

“The reconstruction of 430 m of the same street was completed in February this year, from the crossroads in Vojvođanska street to the intersection with Kragujevačka street. The contracted value of these works amounted to 378.632,40 euro,“ they added.