Wind farm on Možura will be finished by the end of July

Foto: Arhiva Dnevnih novina

Chinese company “Shanghai Electric Power Engineering”, the main contractor in the construction of the wind farm on Možura, has set up 13 out of planned 23 wind generators so far. The objective of the investors is to complete the works by the end of July.

It’s not familiar how much the investment amounted but the total investments should be 89 million EUR.

By means of the contract on land lease and construction of wind farm on Možura, which Montenegro signed eight years ago with the Spanish company “Fersa Energias Renovables” and company “Čelebić” from Podgorica, the state land had been given into a 20-year long lease, for the purposes of the construction of wind farm of the installed power of 46 megawatts.