Work pace in the project of construction of priority section of the highway Bar – Boljare has increased once necessary construction permits were issued, Dnevne Novine daily reports.

Ministry of Traffic issued 17 of the total of 19 permits. The remaining two will be issued during July.

From the total of 16 tunnels, construction is being done on 9: Vezesnik, Mrke, Klopot, Vilac, Vjeternik, Mrki krs, Kosman, Mala trava and Jabucki krs.

The most demanding construction on the section is bridge Moracica (height of the third pole is 161 m, length of the bridge is 960 m and width 23,4 m). Construction is currently ongoing in all five poles, of which three are built halfway in height.

According to preliminary data of CRBC, the value of works delegated to subcontractors so far is 34,35%, which means around 250 million will remain in the financial circles in our country.