Two offers submitted in response to tender notice

According to the executive director of Monteput company, Mr Jonuz Mujević, so far two offers have been submitted in response to the second tender notice to install a permanent power supply system on the priority Smokovac-Mateševo motorway section.

“Bid opening took place yesterday, and the decision on the responsible contractor shall be known in seven days at the latest,” Mr Mujević told Pobjeda daily.

Two local companies, that is, consortiums have submitted their offers so far, according to him. The state-owned company Monteput cancelled the first tender procedure for the construction of energy infrastructure on the Bar-Boljare motorway as no bidder submitted suitable offer.

The estimated value of construction works is €38.23 million and the company [Monteput] will ensure the funds from the Investment and Development Fund, IRF.